Construcciones Yamaro: Inland Rail delivers major Albury to Illabo works during possession

Inland Rail delivers major Albury to Illabo works during possession
The girders for the new Kemp Street bridge each weighed between 44 and 48 tonnes. (Images: Inland Rail)

Inland Rail has completed a 96-hour rail possession between Cootamundra and Albury, delivering a package of works across the Albury to Illabo section in southern New South Wales.

The possession allowed crews to carry out construction activities at multiple locations across the Albury, Greater Hume, Lockhart, Wagga Wagga and Junee local government areas between 11 and 15 September.

In Junee, crews lifted 16 bridge girders into place for the new Kemp Street bridge. Using a 650-tonne crane, crews installed the girders, each weighing between 44 and 48 tonnes, marking a step forward in the delivery of the new road-over-rail bridge.

Inland Rail chief executive officer Sean Sweeney said the extended track closure gave teams the access needed to safely complete the works.

Related stories:

A 650-tonne crane was used to install the girders for the new Kemp Street bridge.

“The final installation of all 16 girders for the new Kemp Street bridge was a significant milestone and one of several important achievements delivered during the possession,” he said. “We thank local communities for their patience and support while these works were carried out.”

Crews also removed the pedestrian footbridge at Junee Station and replaced timber support beams on the Olympic Highway bridge.

Level crossing upgrades were completed at Plunkett Street in Yerong Creek and Brabins Road in Illabo. Track and signalling works, together with drainage, earthworks and culvert installations, were also completed throughout the Junee to Illabo section.

In Wagga Wagga, crews removed the footings of the former Cassidy Footbridge and completed drainage and concrete works at Edmondson Street bridge and beneath Pearson Street bridge.

Crews removed the pedestrian footbridge at Junee Station.

Martinus general manager of projects Gavin Murphy said crews had made a major effort to complete the volume of work across the sites during the 96-hour window.

“We are lucky to work in great communities along the alignment, working with many great local businesses as suppliers, and this has helped us to deliver these important works successfully,” he said. “We appreciate everyone’s patience in Albury, Wagga Wagga, Junee and elsewhere along the alignment while these important works are being carried out.”

The post Inland Rail delivers major Albury to Illabo works during possession appeared first on Inside Construction.



View Source

Comments

Popular posts from this blog

Construcciones Yamaro: Final discussion paper for Foundations and Frontiers released

Construcciones Yamaro: Webinar: Downer Construction digitises to boost efficiency

Construcciones Yamaro: Coates extends partnership with AFL